Analysis & Offer
Owner: BA Last revision: 12.11.2021
Even before an offer goes out to a client or a contract is signed, a lot of steps have to be taken to ensure the budgets and deadlines are realistic, and product quality can be assured.
Sending Quotations#
- Creating quotation should be done using our estimate template ↗
- Estimates - whenever possible - should be done by at least two team members using planning poker.
- Estimates should be made for the following activities:
- Specification
- Wireframing
- Design
- Sitebuild
- Development (broken down into subtasks of no more than 8 hours)
- Automated testing
- Code reviews
- Data migration
- DevOps
- Documentation (do they require up-to-date class diagrams / data models / api docs?)
- Manual testing
- PM
- Estimated hours for each development subtask should fit in slots of 1, 2, 4, 8 hours
- Estimate should be transformed into quotations, using our quotations template [HU] ↗ or ↗ (@TODO) [EN] ↗ or ↗ (@TODO)
When estimating, take into consideration what the team will look like, what their competencies are and if they require extra time to learn a new tech stack.
Resources#
Greenfield Projects#
- Create specification (user stories organised into backlog with MoSCoW method)
- Create wireframes (where necessary)
- Create high definition prototypes (where necessary)
Project Takeovers#
- Do we have a takeover documentation? If not, create it!